Val-d’Or, November 8, 2023

As part of our ongoing efforts to keep the community updated about  our activities in the field, the O3 Mining team would like to inform you of the work that will be carried out over the coming weeks and winter at the Marban Alliance project.

 

From now until the end of December, the work planned includes:

  • Forest clearing to prepare roads and drilling sites;
  • Exploration drilling: 1 drill rig on Norlartic Extension (see figure 1);
  • 12 geotechnical drillings: 1 drill rig to carry out 9 soil drillings and 2 water characterization drillings (see figure 1);
  • Ongoing air quality monitoring;
  • Forest clearing scheduled for December 15 in preparation for roads and drilling sites, subject to approval of our permit requests.

Figure 1 – Planned work areas autumn 2023

 

Winter activities: January to April

Definition drilling campaign on the Malartic H Zone:

We will carry out definition drilling on the Malartic H zone to confirm the resource announced in the June 20, 2023 press release.   The objective of the definition drilling campaign will be to provide a better definition of the potential deposit. Three drill rigs will be in the identified area from January 4 to April. The map shows the location of the drilling zone, as well as the roads that will be prepared to allow the drills and machinery to move around the identified area.

The map below shows the areas where works will be carried out starting in January, in the Malartic H zone.

Figure 2 – Malartic H Zone

 

We will carry out geotechnical drilling to determine soil composition and install observation wells to study underground water.

  • 27 geotechnical drillings, 3 drilling rigs to carry out 25 soil drillings and 2 drillings to characterize groundwater;
  • 1 geomechanical drill and 1 geological drill;
  • Ongoing air quality monitoring.

 

Figure 3 – Winter 2024 work zones

 

It should be noted that the work may change depending on the results obtained and the financing of our activities. We commit to communicating any changes to the planning presented in this communication.

 

If you have any questions or comments about the informations below or the Marban Alliance project, please contact Annabelle Brochu, community liaison agent, at (819) 355-1837 abrochu@o3mining.com.

For media inquiries, please contact Geneviève Tétreault, Public Affairs and Communications Manager, by telephone at 819-763-8161 or by e-mail at gtetreault@o3mining.com.

Recent posts

Communication to the community – Community Relations Office opens in Dubuisson

Val d’Or, June 12, 2024 The O3 Mining team is proud to announce the opening of its brand-new community relations office for the Marban […]

View the post June 12, 2024

O3 Mining Reaffirms Commitment to Responsible Mining Practices

O3 Mining Inc. is pleased to reaffirm its commitment to harmonious and responsible mining practices. To that end, O3 Mining wishes to announce in respect of its non-core Harricana project in Val-d’Or, Québec that it has made a firm commitment not to engage in exploration activities on any of its claims held on the local golf course, the Recreational Forest and category 1 groundwater catchment areas.

View the post May 27, 2024

O3 Mining Publishes 2023 ESG Report

The 2023 ESG report is O3 Mining’s fourth report outlining the assessment of ESG performance throughout the years. We are aware that the practice of sustainable and responsible development in our business is constantly evolving, requiring ongoing commitment and reflection. We continue to work with our stakeholders to create a sustainable future while building the projects of tomorrow.

View the post May 9, 2024

O3 Mining Intersects 119.1 g/t Au over 2.5 Metres at Malartic H, Marban Alliance

TORONTO, April 17, 2024 /CNW/ – O3 Mining Inc. (TSXV: OIII) (OTCQX: OIIIF) (“O3 Mining” or the “Corporation”) is pleased to announce that it has received partial assay results from its 24,505 metre drilling campaign completed between January and March 2024 on the Malartic H area within the Marban Alliance project, in Val-d’Or, Québec, Canada.